How Architects Can Plan a Clinic Expansion Beside a Historic Wing

A clinic expansion beside a historic wing gets hard at the seams. This guide shows how architects can test phasing, infection control inputs, design authority and scope before a design-build team commits to a GMP.

Share
Restored red brick industrial building with a modern glass and steel gabled addition set into its historic facade
A glass addition set into a historic brick building · Photo: Mike van Schoonderwalt on Pexels
Share

Imagine a 15,000-square-foot addition to a regional clinic. The hard problems multiply when that addition attaches to an older wing with historic character, when patients and staff keep using the building every day of construction, and when the work is delivered through design-build with a guaranteed maximum price (GMP). Those problems collect at the seams: where new structure meets existing fabric, where construction zones meet exam rooms, and where design intent meets a price that someone has to stand behind.

This guide explains how architects and project teams can test those seams before anyone commits to a GMP. It is written for architects working inside design-build teams, architects advising owners, and students learning how a delivery method shapes design responsibility.

Start With the Clinic That Has to Keep Running

Before massing the addition, map the clinic as it works today. Record departments, hours, patient populations and adjacencies. Then mark the circulation that cannot be interrupted: the main entrance, accessible routes, emergency egress, drop-off and ambulance access, staff paths, clean and soiled flows, and deliveries. Draw the phasing as a sequence of usable clinic configurations rather than only a set of construction zones. Each phase should show which spaces are in use and which are under construction. It should also show how patients reach care and how staff move supplies without crossing work areas.

Visitor waiting in a clinic corridor while staff in blue scrubs attend a patient in a wheelchair beside a stretcher
A clinic corridor in daily use, the kind of route phasing has to keep open · Photo: RDNE Stock project on Pexels

Give utility tie-ins their own phasing layer. Mark where new systems connect to existing ones and which departments each shutdown affects. Note the backup plan in case a scheduled outage has to move.

The architect does not decide infection control alone. The facility’s clinical and infection-prevention team should lead the infection control risk assessment (ICRA). The architect and builder supply information about the scope, duration and location of the work. The CDC’s environmental infection control recommendations describe the role of a multidisciplinary risk assessment in construction and renovation. The architect’s job is to make the resulting requirements buildable. That means locating barriers, documenting pressure relationships, laying out debris routes and planning phases that support them. Measures depend on the patient population and on the authorities having jurisdiction, so treat ICRA outcomes as inputs specific to this project, not as a standard detail.

Clarify Design Authority Inside the Contract

In design-build, the owner holds a single contract covering both design and construction. The Design-Build Institute of America’s owner FAQ explains how that structure assigns responsibility. The single contract does not settle who holds design authority within the team, though. The architect may be a subconsultant to the builder, part of an integrated firm or a joint-venture partner. Each arrangement changes how the team resolves disagreements about quality, preservation or clinical function.

Builders usually describe early collaboration as the premise of the method. To assess design-build coordination for occupied renovations, start with how the team describes early designer-builder collaboration, then ask for project-specific evidence. A general contractor page can explain the model, but it cannot establish clinical or preservation experience on its own. The architect has to turn the general model into specifics:

  • who signs and seals the documents
  • who decides when a cost-driven substitution changes design intent
  • how clinical stakeholders reach the design team directly
  • what happens when professional judgment conflicts with the schedule

Write these answers down before schematic design is complete.

Investigate the Historic Wing Before Pricing It

Older buildings hide things. Teams often find undocumented renovations, deteriorated masonry, structure that differs from the archival drawings, and hazardous materials such as asbestos or lead paint. Where the addition meets the historic wing, those unknowns affect the foundations, the structural connection, the envelope and how building systems extend.

Worker on a green aerial lift repairing the ornate stone and brick facade of a historic building
Repair work on a historic brick and stone facade · Photo: Whittington on Pexels

Push for investigation before the GMP. Review existing drawings, run targeted probes and selective demolition where operations allow, commission hazardous materials surveys, and assess the features that define the wing’s character. Then decide which spaces, finishes and elevations matter most and how they will be protected during construction.

What applies depends on the building. Its designation, its location in a historic district, its funding sources and local review all shape the requirements. Where they apply, the Secretary of the Interior’s Standards for Rehabilitation provide a framework for retaining historic fabric and designing additions that are compatible yet distinguishable. Where they don’t apply, they are still a useful reference. Confirm early whether a state historic preservation office or a local commission has a role, and put that review on the schedule.

Make Scope Uncertainty Visible

Two GMPs with similar totals can describe very different projects. The differences sit in the scope definitions, allowances, contingencies and exclusions. Architects can bring those into view instead of leaving them buried in a cost narrative.

Two people in hard hats reviewing a printed plan in an unfinished interior with bare concrete floors and white walls
Reviewing drawings on site before the price is fixed · Photo: Pavel Danilyuk on Pexels

Tie each allowance to a drawing or specification reference, and note how its figure was derived. Clarify who controls contingency and what happens to unused amounts. Flag exclusions that tend to fall at the interface: hazardous materials abatement, concealed conditions, owner-furnished medical equipment, IT and low-voltage systems, and permit or utility fees. Agree on how changes are priced, approved and documented. A long allowance list on a historic wing is not automatically a problem, but it does mean the number is less certain than it looks.

A Decision Sequence Before the GMP

  1. Operational baseline. Existing-conditions plans are annotated with departments, hours, critical circulation and utility dependencies, then reviewed by clinical leadership.
  2. ICRA inputs. Phasing and work-zone drawings go to the infection-prevention team, and its requirements are built into the phasing plans.
  3. Investigation results. Probe findings, hazardous materials surveys and the preservation review are summarized with their cost and schedule implications.
  4. Design authority confirmed. Contract roles, sign-off on substitutions and the owner’s direct access to the design team are documented.
  5. Schematic gate. Design, estimate and phasing are reviewed together, and clinical stakeholders get enough time to respond.
  6. Design development gate. Details at the connection between the addition and the wing are developed far enough to price. Allowances shrink where investigation allows.
  7. GMP decision. The owner decides whether the documents are mature enough to support a GMP. An agreed exit option, such as taking completed design documents to another builder, protects the owner if the number doesn’t work.

GMP timing is a trade-off. A number set early in schematic design has to carry more contingency or more allowances. A number set after investigation and design development usually rests on firmer ground, but it takes longer to reach. Neither approach guarantees a lower cost.

Communication and Handoff

Agree on four things early: who the owner’s day-to-day contact is, how cost and schedule updates are reported, how staff and patients hear about disruptions, and how a surprise in the historic wing will be documented and priced. At handoff, deliver record drawings that capture the concealed conditions found during construction, along with the phasing and preservation decisions behind them. The next team to open those walls will need them.

The architect’s contribution to a design-build GMP is more than a design that can be priced. It is a set of documents that shows the owner what is known, what is not yet known and what the number actually covers.

Share
Written by
LA Editorial Team

The Learn Architecture editorial team is a group of architects, designers, and writers who research, write, and review content on architecture, design, technology, sustainability, and education for students and professionals worldwide.

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Articles
A modern stone office building behind black iron gates and lamps, with a green sign reading The Rolls Building, Royal Courts of Justice, and a Gothic building beside it
Architecture NewsConstruction

Hawkins\Brown Fails to Stop £7.35m Defects Claim Over Islington’s Wenlock Building

A High Court judge has refused Hawkins\Brown's application to strike out a...

A long apartment block of three stacked, offset bars clad in brown and orange panels beside a canal, with a yellow industrial roller sculpture in front
Architecture NewsConstruction

Urban Splash Ordered to Pay £46.5m Towards Fire Safety Repairs at Seven Manchester Blocks

The First-tier Tribunal has made remediation contribution orders against five Urban Splash...

Two-storey light wood frame house under construction, with upper floor stud walls standing on the deck above the ground floor walls
Construction

Balloon Framing vs Platform Framing: Differences, History and Fire Safety

Balloon frames run studs from sill to roof plate; platform frames stack...

Learn Architecture is a global architecture learning platform and marketplace for content creators.

Subscribe to Our Updates

Enjoy a daily dose of architectural projects, tips, hacks, free downloadble contents and more.

Copyright © Learn Architecture Online. All rights reserved.
Made with ❤️ by learnarchitecture.online

iA Media's Family of Brands