Home Architecture News BDP and Galliford Try Fail to Have Aberdeen Hotel Cladding Claim Dismissed
Architecture NewsConstruction

BDP and Galliford Try Fail to Have Aberdeen Hotel Cladding Claim Dismissed

Lord Richardson refused to throw out Leonardo Hotel Management's claim over the cladding of its Union Square hotel in Aberdeen, and let BDP pursue Kingspan over Kooltherm K15. No defect has been proven.

Share
A glazed entrance hall with a deep overhanging roof and the words Union Square, fronted by a cobbled forecourt with traffic cones
The Union Square development in Aberdeen, which includes the hotel at the centre of the case · Photograph: Dr Neil Clifton, CC BY-SA 2.0 via Wikimedia Commons
Share

An attempt by BDP, the architect, and Galliford Try, the contractor, to have a cladding claim over an Aberdeen hotel struck out as too late has failed. In a ruling dated 20 October, Lord Richardson of the Court of Session refused their motions and those of insulation maker Kingspan, sending the case to a full hearing of evidence. Nothing has been proven: the alleged defects, and the alleged concealment of them, remain allegations to be tested at trial.

The background to the cladding claim

The claimant, Leonardo Hotel Management (UK), runs the Leonardo Inn Hotel in the Union Square development, which also redeveloped the city’s bus and railway stations. BDP designed the scheme, while a subsidiary of Galliford Try delivered it under a design and build contract. Practical completion of the hotel was certified in February 2009, and in December that year Leonardo took a lease that made it responsible for repairs, backed by collateral warranties from both firms.

Leonardo says the cladding is defective, that the two companies broke their obligations and that they concealed the faults; it wants them to pay for the repairs it says it must carry out. Construction News reports that the cladding was first looked into after the June 2017 fire at Grenfell Tower. Proceedings were raised in February 2021, some 12 years after completion.

A granite railway station building with arched windows beside a modern glazed block, across a cobbled square
Aberdeen railway station beside Union Square; the scheme also redeveloped the bus and rail stations · Photograph: Dr Neil Clifton, CC BY-SA 2.0 via Wikimedia Commons

Why the time bar did not end the case

Scotland’s 1973 Prescription and Limitation Act means most such claims expire after five years, and the defenders argued that Leonardo had simply left it too late. Lord Richardson accepted much of that reasoning. He agreed the warranties let both firms rely on time-bar defences, and held that Leonardo’s loss occurred when it signed the lease.

However, the Act stops the clock while a claimant is kept from suing by error induced by the other side’s words or conduct. Leonardo alleges that Galliford Try covered defects with other materials as work progressed and did not report them, and that BDP failed to spot and report defects on its inspection visits. Construction News quotes the judge saying Leonardo had an arguable case that “neither it nor the landlord were physically able to see the defects which were incorporated into the building as it was constructed.” He found that enough to require evidence, adding that a failure to act can count as relevant conduct.

Inside a bright shopping centre with a timber ceiling, escalators and a café, and people walking with luggage
Inside the Union Square shopping centre · Photograph: Novak123, CC BY-SA 4.0 via Wikimedia Commons

BDP’s own claim against Kingspan

After the Grenfell Tower Inquiry reported, BDP brought Kingspan into the action. It alleges fraudulent or negligent misrepresentation in technical information about Kooltherm K15 insulation, and says those statements were why it chose the product. Kingspan’s case was that this claim was also out of time and that a 2017 report should have alerted BDP. The judge disagreed at this stage, holding that a misrepresentation can continue to have effect and that the report was not clear enough to show what BDP knew; he noted BDP’s reliance on a later report that found K15 compliant.

As Construction News points out, the ruling settles neither whether the cladding was faulty nor whether any of the firms is to blame. Leonardo declined to comment to the AJ, and BDP, Galliford Try and Kingspan had been approached.

Share
Written by
Bahattin Duran

Bahattin Duran is an architect and Editor in Chief of illustrarch who also leads learnarchitecture.net, where he writes and oversees content. He holds a Bachelor's Degree in Architecture from Düzce University.

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Articles
Precast hollow core slabs stacked on a flatbed truck, the round cores visible at their saw-cut ends
Construction

Hollow Core Slab: Sizes, Spans and Design Considerations

Precast hollow core planks come 1200 mm or 4 ft wide and...

A low beige building with a long glazed ground floor and a curved pavilion, behind a planted courtyard at sunset
Architecture NewsCareer

Scott Brownrigg’s Pre-Tax Profit Rises to £4.4m as UK Fee Income Grows 37%

Accounts for the year to 31 January 2026 show Scott Brownrigg's turnover...

A pale stone 1930s building on a street corner lit by low sun, with tall windows and a carved figure high on the facade
Architecture NewsCareer

RIBA Reports Itself to the Charity Commission Over Allegations of Potential Fraud

The Royal Institute of British Architects has made a serious incident report...

Public restroom with urinals behind privacy screens, a central lavatory counter and a row of toilet compartments with blue partitions
Construction

Plumbing Codes for Architects: IPC, UPC and the Clearances That Shape Plans

The IPC and UPC agree on 15 inches from a toilet centreline...

Learn Architecture is a global architecture learning platform and marketplace for content creators.

Subscribe to Our Updates

Enjoy a daily dose of architectural projects, tips, hacks, free downloadble contents and more.

Copyright © Learn Architecture Online. All rights reserved.
Made with ❤️ by learnarchitecture.online

iA Media's Family of Brands